Contract Nexus provides practical governance tools and construction-law information to support decision‑making. It is not legal advice and should not be relied on as legal advice. If you are close to a deadline, escalation, or proceedings, email info@contractnexus.co.uk or speak to counsel.
Nexus answer:
A valid Payment Notice is one that meets the contract and statutory requirements on timing, content, and service. In practice, it’s not “pretty formatting”, it’s whether the notice clearly states the amount due and the basis for it, served on time, in the right way, to the right recipient.
Next 48 hours:
Evidence checklist:
Traps:
Tool + trigger:
Run Payment Pack Builder. If you’re within 7 days of final date for payment, trigger Payment Protection Pack.
Nexus answer:
A Pay Less Notice that’s served outside the contract/statutory deadline is often a procedural failure, meaning the payer may have to pay the notified sum (or the applied-for sum if no valid payer notice exists), subject to the specific contract mechanism and facts. Your job is to make the issue binary: deadline missed, service not proved and content not compliant.
Next 48 hours (do this):
Evidence checklist (minimum):
Common traps:
Tool + trigger:
Run Notice Calendar Builder + Notice Compliance Risk Matrix. If risk is Amber/Red, trigger Payment Protection Pack.
Nexus answer:
If the payer fails to issue required notices, the payment mechanism can default in a way that forces payment of the notified or applied-for sum, then valuation arguments move to a separate forum (often via “true value” routes depending on timing and case law). Your advantage is procedural clarity; use it fast and cleanly.
Next 48 hours:
Evidence checklist:
Traps:
Tool + trigger:
Run Adjudication Readiness Checker if payment is not made by the final date.
Nexus answer:
Yes, in many situations, the payer can seek a decision on the “true value” after a technical loss, but the sequencing and conditions matter, including whether the payer first pays the amount due under the notice regime (the exact position depends on the case law and the facts). A clean strategy is: secure the procedural win and prepare for the valuation counter‑move.
What to do now:
Trigger:
If you don’t already have a measurement-ready valuation pack, trigger the Payment Protection Pack.
Nexus answer:
You prove it like a forensic timeline: (1) baseline scope, (2) change event, (3) causation to extra work/time/cost, (4) contemporaneous records showing it happened, (5) contract route for valuation. No written instruction means you must over-invest in evidence discipline. Don't make it a habit, though; always kindly ask for a written instruction.
Next 48 hours:
Evidence checklist:
Traps:
Tool + trigger:
Run Variation Evidence Indexer. If >£50k exposure or time impact is material, trigger Change Control Pack.
Nexus answer:
Treat it as a valuation method problem: determine whether contract mechanisms allow “star rates” or fair valuation, then anchor the calculation in actual records (labour/plant/materials/subcontract). The enemy is unsupported “commercial” numbers.
Next 48 hours:
Tool + trigger:
Use Variation Evidence Score Matrix → trigger Change Control Pack if risk is Amber/Red.
Nexus answer:
Make scope creep visible: register it, price it, and time-stamp approvals. Final account “surprises” only work when governance is missing.
Do-now:
Tool:
Variation Evidence Indexer + Checklist Pack.
Nexus answer:
Concurrency is where weak claims die. You survive by (1) credible baseline + updates, (2) event-based timeline, (3) critical path logic, (4) clear causation chain, (5) evidence density. Don’t argue concurrency in the abstract; prove sequences.
Next 48 hours
Traps:
Tool + trigger:
Run Delay Entitlement Matrix. If Amber/Red, trigger Delay & Disruption Forensic Pack.
Nexus answer:
You need two comparable “miles”: a period of good productivity and a period of impacted productivity, with consistent measurement. The strength comes from clean contemporaneous records, not expert poetry.
Minimum evidence:
Tool:
Delay & Disruption Checklist + Evidence Index Template.
Nexus answer:
Concurrent delay is when employer-caused delay and contractor-caused delay overlap in time and impact. The consequences depend heavily on contract drafting and the factual critical path position. Some contracts explicitly allocate concurrency risk; courts have upheld parties' ability to allocate it by contract.
Action:
Don’t argue definitions. Build a timeline and logic model, then test concurrency scenario-by-scenario.
Nexus answer:
Defend by proving entitlement to EOT (extension of time) and/or that LDs (liquidated damages) do not apply in the way alleged due to contract interpretation, termination effects, or causation. The Supreme Court in Triple Point clarified principles around LD clauses and termination interpretation.
Tool:
Delay Entitlement Matrix + Delay Checklist.
Nexus answer:
Contain exposure and preserve options: lock evidence, secure site status, map unpaid exposure/materials, review termination/suspension rights, and build continuity plans. Insolvency punishes delay.
48-hour action list:
Tool + trigger:
Run Solvency Forensic Audit (Rapid). If high unpaid exposure or key trade failure risk, trigger Insolvency Response Pack.
Nexus answer:
Insolvency complicates enforcement, but it does not automatically remove adjudication jurisdiction. The Supreme Court in Bresco confirmed that adjudication can still be available even where insolvency set-off exists. Supreme Court UK
Practical implication:
Assume enforcement and stay arguments will be fought. Build a stronger bundle and plan for security/stay risk.
Nexus answer:
Enforcement may be resisted, often via stay/security arguments. Insolvency context raises practical barriers. The strategic response is to (1) strengthen evidence and (2) anticipate enforcement hurdles early using bundle discipline. Bresco is the key starting point. Supreme Court UK+1
Nexus answer:
Potentially, yes. Section 135 extended the limitation for certain defective premises claims, including a 30-year retrospective window in relevant cases, which can bring older projects back into exposure.
Action:
Run the Retrospective Exposure Calculator, issue a Document Hold, and build the recovery chain map.
Copyright © 2026 Contract Nexus - All Rights Reserved.
Construction Contracts & Claims Specialists